Project Overview


Scope of works included the fabrication and installation new hot dipped galvanised posts from Practical Engineering`s design, that supported the shade sail covers at a water treatment plant.

Capalaba Water Treatment Plant Maintenance
Capalaba Water Treatment Plant Maintenance
Capalaba Water Treatment Plant Maintenance
Capalaba Water Treatment Plant Maintenance
Capalaba Water Treatment Plant Maintenance
Capalaba Water Treatment Plant Maintenance
Capalaba Water Treatment Plant Maintenance
Capalaba Water Treatment Plant Maintenance

Replace Shade Sail Posts at a Water Treatment Plant

Overview of Project:

Fabricate and install new shade sail posts at a water treatment plant.

Scope of Works:

Existing posts located on top of the tank walls on 2 x clarifier tanks at a water treatment plant had broken out the concrete and were at risk of falling into the clarifiers.

Neumann Water fabricated and installed new Hot Dipped Galvanised posts from Practical Engineering’s design.

22 posts in total to be installed.

Old posts were removed, and shade sail was reconnected to all the new posts.