New Transfer Pump Bypass at Bundamba WPS
Principal:
Veolia Water
Location:
Bundamba West Pump Station, Qld
Project Overview









Bundamba West Pumping Station – New Transfer Pump Bypass
Overview of Project:
Currently, temporary mapress 316 SS bypass pipework within the Bundamba West pump station is used to supply water from the Eastern Pipeline to the Bundamba Treated Water tanks. It was identified that fit-for-purpose designed pipework was required to replace the temporary solution for ongoing supply. The pipework changes will ensure the ongoing supply of PRW to the Bundamba Treated Water Tank TNK5201 for supply to Swanbank Power Station.
Scope of Works:
The objective of the project was to undertake the recommended pipework changes ensuring the ongoing supply of PRW to Swanbank Power Station, as the existing temporary pipework was not designed for long-term use.
Construction Activities:
We confirmed all site measurements and site information to ensure successful execution of works and verify Cardno drawings for the development of fabrication drawings for spools, brackets and platforms. This was carried out with a site scan from Ferrier Engineering. Information was required to be supplied from the RPEQ Certifier to the drafter. Neumann Water requested this information be returned in a timely manner, preferably same day, so it would not delay the drafting and drawing development. All requests were submitted via email to the Veolia Project Manager for approval. Drafting was submitted for RPEQ review and certification by Cardno. Once written approval was received, ordering of equipment and fabrication of spooling and platforms followed.
Procurement
- DN300 Control Valve, DN300 Challenger Gate Valve & concrete lined pipe spools.
Site Works
The electrical components were disconnected prior to the arrival on site of Neumann Water. Neumann Water carried out the removal of all redundant equipment and spools to enable the existing concrete plinth to be cut down prior to the installation of new equipment and spools.
Mobilisation and Site Set-Up
- We obtained Permit to Work with any high-risk permits (JSEA or SWMS were issued for review prior to work commencing);
- Set up work area (noting that other works were planned to occur in Bundamba West Pump Station in the same period);
- NOTE: All isolations and drain down works were completed by Veolia Water. Workers were required to lock on to the lock box and follow all the principal’s LOTO (Lock Out Tag Out) procedures.
Installation of New Equipment and Pipework
All new pipework and equipment were installed as per design requirements.
Testing
Pipework pressure test reports (new spool pieces), onsite hydrostatic tests at completion of works prior to commissioning, and basic equipment testing (for all valves supplied).
Demobilisation
Removal of all site generated waste; return of work area to clean and tidy state.
Conclusion/Outcome:
The project was completed on time and on budget. Veolia Water was happy with the works completed.